We forgot to close one task in sprint but it was complete. How i can add it to closed sprint without to reopen it? We don't want to lose story point that's why want it back.
Community moderators have prevented the ability to post new answers.
Hi Erop,
There is not a way to add a task to a closed sprint; you will have to reopen it. You'll need to either allow parallel sprints or close the current sprint before you reopen the previous one.
-Scott
I was able to associate a test case to a past sprint by mistake, but now I want to remove this association from the closed sprint
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Perhaps this is a software failure, PMs usually need to log tasks that were not considered in the previous sprint planning.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.