The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
We are working with two week sprints in a Scrum board and recently had a situation come up where one of my developers uncovered a chunk of work that wasn't originally considered during sprint planning on Task 1 - in theory shouldn't have affected his original story.
Trying to determine the best approach on adding this task 2 in, which will take about 20 hours, while reserving our reports. Would love to be able to show the work done during this sprint on Task 1 even though now it will not be completed until the next sprint. Task 1 will have to be paused until Task 2 is complete.
Thank you for your reply! This actually makes the most sense and I think it would solve the need for having reports show what happened a bit more accurately.
👋 Hi there Jira Community! A few months ago we shared with you plans around renaming epics in your company-managed projects. As part of these changes, we highlighted upcoming changes to epics on...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events