how to change an in progress task to sub task

There are a few isolated tasks which are related. Therefore, I want to make this into a sub-task and assign under a new task. How do I do that? 

Tried move task but doesnt help

2 answers

0 votes

Go to the issue view and use the "more" menu (...) to select "convert to sub-task".  It will ask you what type you want to change it to, and what parent issue you want to move it under.

If you don't have that option in the menu, then your project "issue type scheme" does not have any sub-task types in it and/or "sub tasks" are disabled in global admin.

Thanks , that worked

0 votes
Warren Levy Community Champion Dec 14, 2017

Hi

I don't use Core, but I'm sure it's the same as the other Jiras. Click on the three dots (or More in older versions) at the top right hand side and there should be a menu item Convert to sub-task. it shouldn't make a difference which state it's currently in. You would only see this menu item if you have the correct permissions.

Thanks , that worked

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Friday in Jira Service Desk

Looking for anyone who has switched from Zendesk to Jira Service Desk

Hi Community! The Jira Service Desk marketing team is looking for customers who have successfully switched from Zendesk to Jira Service Desk!   We’d love to hear your thoughts on the pros and ...

117 views 7 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you