how to add a blocked column on business projects

Jane Conners January 30, 2019

Set up an internal project in jira cloud - business . Want to add a BLOCKED column between IN PROGRESS and DONE that can be transitioned to and from IN PROGRESS or moved to DONE 

1 answer

1 accepted

0 votes
Answer accepted
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 30, 2019

Hello Jane,

The board columns of your Business project are based on the workflow statuses of the project.

That been said, you only need to add the status Blocked to your project's workflow (Project settings > Workflow) with the transitions to the statuses In Progress and Done and a new column will be raised in your board, just like below:

Screen Shot 2019-01-30 at 18.47.23.png

Screen Shot 2019-01-30 at 18.45.42.png

Let me know if you still have any questions.