When I try to complete a sprint it says "Sprint cannot be completed as there are incomplete subtasks". All my issues are either done or cancelled. I am using simplified workflow, with cancelled and done "set resolution" fields checked in the board configuration page. The cancelled status is not displayed on the kanban board, i.e is not in a column. When i add it to the done column, I am able to complete the sprint. I do not want the cancelled tasks to show up on the kanban board.

So my question is, why can't I complete the sprint when the cancelled status is not displayed on the kanban board? This looks like a bug.

I am running the latest version jira server.

 

1 answer

1 accepted

1 votes

It's because an issue has to be in the right hand column for it to be considered "done".

Best option is probably to put the cancelled status in the done column and create a quick-filter to hide it from the board.  Even when hidden, it's still in the column, so you'll be able to close the sprint.

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

265 views 0 12
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot