Why Won't My Sprint Close

Hello,

 

All of the parent issues and sub-tasks in our sprint are in a closed state. I keep getting an error message that all sub-tasks need to be closed so I can close my sprint. These sub-tasks are already closed. Any ideas?

3 answers

1 accepted

1 votes

The subtask might not be appearing in the board as it doesn't meet a search criteria? Can you drill down into the stories and check?

Could possibly a ticket that was moved to another project and therefore dropped off the board but is still attached to the sprint behind the scenes. The 'move' function in JIRA is known to have issues around permissions and more.

1 votes

As well as what Sten and Jobin have suggested, could you go back to the board and make sure all the issues are in the far right-hand column (Done)

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

662 views 4 15
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot