What is the difference between estimate and story points?

You cannot edit the estimate once it is in an active sprint.  However, you can edit the story points.  What's the difference between the two fields?

2 answers

1 accepted

0 vote

The original estimate is exactly that - what you think it will take in terms of time.  You can't edit it because it doesn't make sense to do so, it's trying to trap what you thought originally.  But you can change the remaining estimate and log work to show effort made towards it.

Story points are far more simple - an issue will take X story points.  If you want to change it, you can.  That's about it, it doesn't do any more.

I believe the estimates are tied to actual time logged to the stories, whereas story points are not.

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Feb 15, 2018 in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

1,134 views 6 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot