What is the difference between estimate and story points?

You cannot edit the estimate once it is in an active sprint.  However, you can edit the story points.  What's the difference between the two fields?

2 answers

1 accepted

0 vote

The original estimate is exactly that - what you think it will take in terms of time.  You can't edit it because it doesn't make sense to do so, it's trying to trap what you thought originally.  But you can change the remaining estimate and log work to show effort made towards it.

Story points are far more simple - an issue will take X story points.  If you want to change it, you can.  That's about it, it doesn't do any more.

I believe the estimates are tied to actual time logged to the stories, whereas story points are not.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

145 views 1 17
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you