Two Scrum Boards with Two Workflows

Qais Alkhatib
Contributor
October 14, 2018

Hello guys,

Currently, I am doing new setup for new board and workflow for my team, and I don't want to play with the existing board and workflow. My question can I additional workflow for the new board without doing conflict with the existing one until i make sure everything is perfect then I will disable the old board and workflow and keep the new one active.

your help would be highly appreciated. thanks a lot.

2 answers

1 accepted

0 votes
Answer accepted
Matthias Gaiser _K15t_
Community Champion
October 14, 2018

Hi @Qais Alkhatib,

you can perfectly create a new board in order to play around and come up with your new structure. However, it is not that easy to try out new workflows. Workflows are tied to the issues based on their issuetype and the project they belong to.

In order to try out your new setup, I'd recommend that you create a test project, associate it with a copy of your workflow. Then you can adjust your workflow and your board there.

After you're done with your setup, you could change the board configuration so that it matches your real project and change the workflow of your real project to this one.

Cheers,
Matthias.

0 votes
Peter Bengov
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 14, 2018

If your board is for the same project and issue type combination - you won't be able to separate the processes. However, if you want to "test" this first you can create a new project with the same issue type scheme as the old one and there assign a new workflow scheme. 

Remember that a board is just a visual representation of the projects and issue types you choose to show in it. So I would suggest the above solution as it would also make your life easier for "hiding" the old tickets from the old board and showing only the "new" tickets on the new board. You only add a something like the section below to your board filter:

project = "NEWPROJECT"
Qais Alkhatib
Contributor
October 14, 2018

thank you Peter, I agree with you, having a test project would be better. I will give it a try, thanks a lot.

Peter Bengov
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 23, 2018

Sure. Happy to help. If you find any answer satisfying please accept for others to enjoy it in the future 