How to handle multiple scrum team on single project

Hello,

I am new to JIRA. I explain my question

I have one project on which 3 different teams are working eg. IPhone, Android, Server

We have Sprint 1 for 2 weeks (means 80 hrs) that have task same tasks for Android and IPhone

API's task for Server to related task assigned to Mobile Team

In Total in have 80*3 = 240 hrs for whole estimate

But now in JIRA if i give 240 hrs then its wrong because my Sprint is of only 2 weeks means 80hrs.

I gave 80 hrs to Android, 80 hrs to IOS, 80 hrs to server

Please suggest and guide me on this.

Thanks 

1 answer

0 vote
Tarun Sapra Community Champion Aug 17, 2016

That's why it's better to use Story points for estimation, because even though you have same tasks but different teams are working on it (Android, iOS) as the final work is for 2 different platforms thus the efforts of both the teams should counted towards the final burndown. My suggestion is to move to story points instead of hours. Maybe some Agile coaches on this forum can share their opinion as well.

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Feb 15, 2018 in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

1,209 views 6 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot