I have configure my project in that way:
2 IssueTypes
"IT A" and "IT B"
2 SubtasksTypes
"STT1" and "STT2"
Now I would like to restrict the creation of subtasks that way
only possible to create "STT1" from "IT A" or "STT2" from "IT B" no other combination authorized
if for example the user try to create "STT1" from "IT B" , he shall get an error
It is possible? how?
Thank you in advance for your answer.
C.Maille
There is no way to do this out of the box. All sub-task types are avaliable for all standard types in a given project.