Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,461,694
Community Members
 
Community Events
176
Community Groups

how to add 'Estimated:' field (original estimate) from time tracking section after creating a task

I want to edit Estimated filed from time tracking section.

I want to add estimated time to few tasks before adding them to sprint

1 answer

1 accepted

0 votes
Answer accepted

Hello,

You should add the Time Tracking field to the Edit screen for your issue type and you will be able to edit the Estimated field, if you push the Edit button for an issue.

Hi,

 

Having created the project, i cant see where to add those fields.

 

I'm an administrator on the project.

 

Thanks

 

Gareth

Suggest an answer

Log in or Sign up to answer
TAGS

Atlassian Community Events