The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results forĀ 
Search instead forĀ 
Did you mean:Ā 

I am using ProScheduler Teamboard, however, I have one project that I cannot plan tasks.

Jason Chayer
Contributor
September 1, 2022

I use ProScheduler to plan out all my tasks. If you go through ProScheduler in the project, you can utilize their Gantt chart. However, I cannot plan tasks for one project. Any other project I can. Any suggestions?

2 answers

2 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Answer accepted
Teresa_DevSamurai
Atlassian Partner
January 17, 2023

Hi @Jason Chayer 

I am working for DevSamurai, the developer of the ProScheduler app that you mentioned in your question. I am pleased to hear that your problem has been resolved. However, I am sorry that you experienced issues for a month.

If you have any additional questions, please reach out to us at atlassian@devsamurai.com

We will answer your question as soon as possible

Many Thanks,

Teresa

0 votes
Answer accepted
Mikael Sandberg
Community Champion
September 1, 2022

In the project that you cannot plan tasks for, make sure that you have permissions to schedule issues if you are using a company-managed project.

Jason Chayer
Contributor
October 18, 2022

Thanks @Mikael Sandberg , the problem fixed itself. Not sure if there was a bug, but I have not experienced the issue for about a month. 