During the Sprint Snapshot Creation

When we start a sprint, we have certain stories considered to be done within the sprint and for that we wants have the Snapshot.

1 answer

1 accepted

1 vote
Answer accepted
Daniel Ebers Community Leader Nov 23, 2020

Hi Reddy,

are you referring to the reports that are available? What is specifically meant by "snapshot"?

Could you explain a bit further what the feature should provide?

In a classic project (Cloud) there is a Sprint report available showing which work was completed in a sprint. Is this what you are looking for?
https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-sprint-report/

Regards,
Daniel

Hi  Daniel Ebres,

The issue we are facing all the time is, that during an active sprint , some stories get in and others get out.

What we would like is get at a particular time, a kind of "snap-shot" so that we know what was added and what was removed.

For Example: At the begining of the sprint we have :

Day 1

Story 1, Story 2, Story 3, Story 4, Story 5

Then, without any information , someone add Story 6,Story 7 and remove Story 4 and Story 5

 

Day x

Story 1, Story2, Story 3, Story6, Story 7

 

Now , we do not know anymore, what was the original scope, as we only can see what's in now. 

We would like to see anytime, What has chanhed with in Active Sprint.

 

Regards,

Reddy

Daniel Ebers Community Leader Nov 30, 2020

Thanks for clarification!

You could vote for this Suggestion: https://jira.atlassian.com/browse/JSWCLOUD-16523
Further discussion, without (in my opinion) sustainable solutions, can be found here.