wrong time estimation

george.svyshch
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 8, 2021

Hi! 

We`ve faced a problem with the wrong time-tracking display in tasks. The original estimate for all subtasks should be 2w 3d 4h but the remaining time is 2w 4d instead. (1st screenshot)

In another task, the original estimate of all subtasks together should be 1w 3d 6h, which is displayed correctly only in the 'time remaining' part, while the original estimate is 2w 1d 6h for no reason. 

Would be really grateful for any help or suggestion.

BR,

George

 

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 8, 2021

Have a look at the histories of the task and sub-tasks.  I suspect you will find someone has changed the estimate fields directly, rather than logging work.