The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

why can't i drag drop story in portfolio board?

ting si
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 24, 2016

i am trying the JIRA portfolio, but the drag and drop doesn't work for me. I can't change story's priority. (people just drag the epic and move to top in the demo video). And it seems like the auto calculation and planning of those releases are based on the ranking of epics/stories.

 

2 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

4 votes
Nithya Ananda
Contributor
October 31, 2016

Rearranging issues in the scope table is possible and determines the priority that issues will be scheduled in your roadmap.

To do this make sure you are sorting your scope table by the rank column (#). When sorting by rank a handlebar will be visible on the left of each issue. 
This will allow to drag and drop to change priority.