when all sub tasks are done move parent to done

Mehmet Yalçınkaya
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 29, 2021

when all sub tasks are done move parent to done? Please help me guide for jira when all sub tasks are to do move parent to 'to do'

1 answer

1 accepted

1 vote
Answer accepted
Jack Brickey
Community Champion
November 29, 2021

Hi @Mehmet Yalçınkaya , welcome to the Community. You can achieve this using automation. If you go to project settings and select automation then click on the library tab you should find a template to achieve your goal. This is illustrated below.

13533F24-2733-4AFB-9FC6-C30445B4308A.jpeg

Mehmet Yalçınkaya
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 29, 2021

thanks for answer 