unestimated issues are not correct in portfolio

kanishk Tandon January 21, 2022

Hello All,

I have an issue where by in Portfolio plan the unestimated issues are showing more than the actual estimated issues.

So I check for all 3 epics there are 4 unestimated issues but in Portfolio plan the unestimated issues are showing as 10.

Anyone has faced similar issue?

 

 

 

1 answer

0 votes
Adam January 27, 2022

Does the filter you use in Portfolio also include Sub-Tasks? If so that might be causing the issue.