The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

time tracking format question

laudren_florent
January 18, 2019

I have edited time tracking format but still estimate time of issues are displayed in standard Jira format.

I'd like to have estimate time and ellapse time displayed in days, not weeks+days.

 Clipboard01.jpg

Clipboard01.jpgClipboard02.jpg

 

 

 

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 18, 2019

Hello Laudren,

Thank you for your feedback about this behavior.

In fact, we've already identified that the only time format available for Time tracking in the New Issue View of JIRA is Weeks/days/hours. That's why we reported this behavior as a bug to our development team:

New issue detail view won't display the Time estimate in hours

Please, watch the bug to be notified about the progress of its fix implementation.

For now, we recommend you to keep using the old Classic View of JIRA to keep displaying the time tracking in the format you want.

Let us know if you still have any questions.

laudren_florent
January 18, 2019

Unfortunally, it is an Entreprise project so the 'old' vue is not a solution