the best way to use Jira as Gantt Chart

Essam Kalla
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 1, 2020

I am new to Jira but have long experience with microsoft project

i am helping nonprofit organization and select Jira for tracking our software implementation project (selection a commercial of the shelf application)

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 2, 2020

Jira does not do Gantt charts off-the-shelf, as Jira is aimed more at the Agile way of doing things where it's clear Gantt charts are useless (They tell you what you would like to happen, without taking into account any reality.  They're obsolete from the point at which you publish one).

So, you'll need to get an app to add the functions to Jira.  There are several in the marketplace  

Essam Kalla
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 3, 2020

Thank you for your reply

i am currently test one of the top Gantt Chart add on for Jira