The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

schedule sprints in Kanban project

JKhan
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 20, 2023

I have an existing Kanban projecct with a Kanban board.   I need to change this project to Scrum with sprints but can only create a Scrum board, but no sprints.

How can I include sprints?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

1 vote
Jack Brickey
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
December 20, 2023

Hi @JKhan , if you are using a CMP project you can create a scrum board and select the project when creating the new board. Once complete you can then chose which board you want to use via the board drop down. You should be able to create and start sprints in the backlog. If TMP project then you can turn on sprints under project settings > features.

Trudy P Claspill
Community Champion
December 20, 2023

@JKhan 

Welcome to the Atlassian community.

Adding to this...

What is the symptom that tells you that you can't create sprints? Do you see the Create Sprint button on the Backlog screen of the Scrum board? Is it enabled or disabled?

You must have the Manage Sprints permission in the project in order to be able to create Sprints. Do you have that permission in the project?