new bulk change prevent me to bulk change status because it has a transition screen before the status changed.

 

i can't use the original method because the new update and when i click use original bulk change from the new method, it does nothing.Screenshot 2026-03-09 084129.png

 

i need to bulk change hundreds of tickets every day and this new method is not helping me.

2 answers

1 accepted

0 votes
Answer accepted
Marc -Devoteam-
Community Champion
March 9, 2026

Hi @Support SPOC 

Welcome to the community.

If your transition in the workflow has screen, you are not able to use bulk functions from the list view or all work view.

Then you need to use the search option to find your work items and via the action (3dots) to the bulk action, as mentioned by @Trudy Claspill 

0 votes
Trudy Claspill
Community Champion
March 8, 2026

Hello @Support SPOC 

Welcome to the Atlassian community.

Can you provide the exact steps you are executing to do the bulk change? There are multiple ways to access that functionality 