my sptint burndown chart not shown guideline line, it is only showing red line

group4
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 26, 2025

i am working on two sprints, it only shows red line on burndown chart not the grey line og guideline line. i need that line 

 

Screenshot 2025-03-26 153950.png

1 answer

3 votes
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 26, 2025

Hello @group4 

Welcome to the Atlassian community.

The guideline is based on the committed work when the sprint starts, drawing a straight line from that value to 0 at the scheduled end date for your sprint.

Looking at the left edge of the chart, when you started the sprint the total of Story Points assigned to issues in the sprint was 0 (or there were no issues assigned to the sprint).

Screenshot 2025-03-26 at 2.02.36 PM.png

 

The gray guideline would be going from 0 at the start of the sprint to 0 at the end of the sprint. It is a flat line with the value of 0 for the duration of the sprint.