The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

missng capability in Jira plans

Yaron Norani
February 20, 2022

Hi,

 

We are using Jira server.

Teams are working SCRUM.

We use Jira Plans (formally portfolio)  to manage the progress - such as PI progress that includes all Epics per PI.

we would like to manage additional things and need a solution for those two items:

1. Option to set the epic summary on the epic progress bar.
    Today, you alwas neeed to scroll to the left side in order to see the issue name / summary.

2. option to manage milestones in Jira plans. My current solution is using a  new issuetype and assign same start / end date, so it will appear as milestone without a duration.

Any other better solutions?

 

Thanks,

 

Yaron

 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Josh Costella
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 20, 2022

@Yaron Norani 

For #1, there is no way out of the box to accomplish that. If you are open to using a 3rd party plugin, something like BigGantt can do both things you are looking for. 

For #2, we also have decided to use a custom issue type for Milestones and this has worked fine for our needs. 

https://marketplace.atlassian.com/apps/1213016/biggantt-gantt-chart-for-jira?tab=overview&hosting=server 

yaronno
February 20, 2022

Thank you Josh.