The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

is there a way to have subtasks appear in boards

Joe Murray
Contributor
February 10, 2017

We want to be able to plan using tasks and subtasks because we want to report time to client based on tasks originally created but to manage work based on subtasks when we break out smaller work packages. Subtasks aren't appearing in boards. How do we enable that? I'm not sure if we are using JIRA Cloud or JIRA Software.

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 10, 2017

From "plan", I assume you mean you want to see subtasks on the backlog?

They're deliberately hidden from the backlog because they are of no use in planning - you can't rank them outside the parent issue, so there's not a lot of use for them.