Good morning all!
I have a question about WBS Gantt chart.
I know that is possible to create a WBS Gantt chart for more than one project. My question is, is it possible to add another project o an existing WBS Gantt chart? if so, how to achieve it?
Thanks in advance,
Ro
Go to the configuration option of your gantt
On the Gantt tab, edit the filter to change the projects included.
Take care to avoid issues being shown in multiple Gantts as they will change the issue gantt data.