I have a project with the hierarchy uber Initiative-->initiative-->Epics-->Stories. I want that the status of initiatives is updated to "In progress" as one of its (child) Epics transit to "In progress". I have implemented the attached automatism but it seem not to respect the "For Parent" condition even if I change the status of Epics that have a parent issue (initiative) as in the attached screen.
Community moderators have prevented the ability to post new answers.
Hi Dominga,
Just move that second condition under the branch and change to a simple Issue Type = initiative
Hello @Dominga Savino
Based on the description that appears with Parent, I believe that option works only when you want to branch to the Parent of a Sub-task type issue.
Refer to this KB for details on how to update the parent of the Epic through Automation for Jira Data Center.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.