The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

how to link task and make them finish-to-start

Chris
January 5, 2024

Is it possible for task to have logic like finish-to-start so that when i adjust one due date the due date of the other task adjust?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Dag Atle Stenstad
Community Champion
January 6, 2024

Hello! Yes, it is possible to achieve this. You can use Jira Automate and set up a trigger for when the "Due date" changes. If it changes, you can then update the "Due date" on all the related issues. How you link issues together is up to you; for example, you can use linked issues or ensure that the issues are part of the same Epic.