Hi,
I am looking to get accumulative time estimate figures per release in my jira project. Can anyone tell me how to do this if this is possible in Jira?
so basically, all I am looking is to have a sum of total time estimate of all issues and total of time spent by assignees on all the issues in a particular release. Releases are shown in the Releases view but it shows only Version, Status, Progress, Start date, Release date, Description, Actions.
any help will be appreciated.
thanks
sanan
Community moderators have prevented the ability to post new answers.
Hi!
I would do this using a free plugin called "project metrics".
It gives you a gadget that shows aggregated values.
Super easy to set up; it will show you the value in week, days and hours.
You can use a JQL query indicating all issues in a certain release.
Then you indicate which field you want to have the sum of (for example, remaining estimate or total estimate etc)
See the screenshot below, I think it is self-explanatory
I hope this helps