The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

how to edit the start and end dates to Tasks?

Girish Pujari
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 9, 2021

how to edit the start and end dates to Tasks?

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
KAGITHALA BABU ANVESH
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 9, 2021

Hello @Girish Pujari ,

 

Welcome to Atlassian Community.

Please check, these below

1. To edit issue --> You need "Edit Issues" Permission

2. Check the Edit Screen associated with "TASK", and check for "Start" & "End" dates that appeared or not. if not add them.

3.  Go to custom fields --> Search for the fields, check for the field contexts, are they displaying required "Task" and "Projects".

 

If all the above are fine. you may be able to "Edit" the start and end dates of the task.

 

Thanks.

Anvesh

0 votes
Girish Pujari
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 11, 2021

The SAVE button was not showing Up. After doing RESIZE on the top right corner. I was able to see it. It looks to be BUG.

 

Thanks