The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results forĀ 
Search instead forĀ 
Did you mean:Ā 
  • Community
  • Q&A
  • Jira
  • Questions
  • how I can change the default start date on Jira timeline, respectively how I can change the range of

how I can change the default start date on Jira timeline, respectively how I can change the range of

Kornel Komlosi
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 8, 2024

timeline start date.PNG

2 answers

2 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
John Funk
Community Champion
January 8, 2024

Hi Kornel - Welcome to the Atlassian Community!

I don't believe you are able to change that - it defaults to the current month. You would need to submit a suggestion to the JWM team. Click the Give Feedback link on the bottom left of your project. 

1 vote
Answer accepted
Walter Buggenhout
Community Champion
January 8, 2024

Hi @Kornel Komlosi and welcome to the Community!

The short answer - unfortunately - is: you can't. From the screenshot you shared, I assume this is a business project (Jira Work Management). While you can change the detail level for viewing the timeline (weeks - months - quarters) near the bottom right corner of the timeline itself, the time range will always default to slightly before today. There is no setting available to change that.

Note that by simply scrolling left or right, you can make the hidden sections visible.

Hope this clarifies!