How to project the plan for a person in JIRA inside a project whether the person is occupied for a specified time or not.

1 answer

0 votes
Deleted user July 18, 2018

Hi @NMR,

Are you able to give me (and the Community) a little more detail to your problem? 

From your current statement, I assume you are trying to plan a resource's/assignee's capacity within Jira. If this is the case, unfortunately Jira does not know of the concept of capacity for a resource, instead you will need to look for an add-on such as Portfolio for Jira or Tempo Planner, though there are more on the Marketplace

Thanks