The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
  • Community
  • Q&A
  • Jira
  • Questions
  • check that sub-task can only be put in 'In progress' if related sub-tasks not assigned current user

check that sub-task can only be put in 'In progress' if related sub-tasks not assigned current user

Marco Brundel
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 25, 2022

Hello,

We would like to check/validate that a sub-task can only be put in 'In progress' if related other sub-tasks have not been assigned to the current user.

So subtask A is assigned to User X.
User X wants to set subtask B to "In Progress" , but we don't want to allow that.

Any idea how to set this up?

Apps JSU, JMWE and Scriptrunner available.

Regards, Marco

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

2 votes
Answer accepted
Marco Brundel
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 25, 2022

Hi,

We solved it with JMWE Related Issue(s) Validator.
See screenshot how we configured it.

Regards, Marco