We recently started to use the new programboard in plans in jira for our PI planning process. The one we now have has been populated with work throughout 8 sprints and looks great. But - I need to change the sprint dates to move one week forward - so that alle sprints start one week forward then the existing plan today. Can I change dates - or do I need to start a new programboard with correct dates and start populating the board one more time?

1 answer

0 votes
Brita Moorus
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 27, 2025

Hi, @cwaldjacobsen! 👋

You're not alone in this - the current version of the Program Board in Jira Plans doesn’t support shifting all sprint dates after initial setup.

Once the Program increment and sprints are mapped into the Program Board, their positions and timing are locked in for that board.

Changing sprint dates in the source boards (Scrum boards) does not update or shift them in the Program Board.

To reflect new start date for your Program board, you'd need to create a new Program Board and remap sprints with the adjusted timeline.

Hope this helps! ✨

 

 

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events