The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

change the working time

Deleted user
September 16, 2019

Is there a possibility to change the working time in the tempo user-defined?

Part time / Full time

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Daniel Wong
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 16, 2019

Hi Lukas,

I'm not sure what you mean tempo user-defined. But if you are looking to change the working days/hours set per user, then you can do it via Tempo Workload Schemes.

KB - https://tempo-io.atlassian.net/wiki/spaces/THC/pages/293930598/Creating+and+Deleting+Workload+Schemes+-+Tempo+Server

For example: If User A only works 8 hours on Mondays and Wednesdays, then you can:

  • Create a new workload scheme that only has Mondays and Wednesdays for 8 hours each day as working days.
  • Add User A as a member of this new workload scheme so that User A only has Mondays and Wednesdays as working days for 8 hours.

Hope that helps.