The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

cannot activate ranking

tsachdvir
January 12, 2020

there is no "boards" section in my toolbar, is that because my license is "Starter License"?

and if not - what do I need to do in order to see the 'boards"?

image.png

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 12, 2020

For Boards there, you need Jira Software, not just Jira Core.

tsachdvir
January 12, 2020

is there another way for me to use "sub-tasks"?

what should I buy? and from where?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 12, 2020

Sub-tasks are part of the Core of Jira, not Software.  You do not need boards to use sub-tasks.  Just make sure there is a sub-task type in the project's issue-type scheme

tsachdvir
January 12, 2020

there is a sub-task type in the project's issue-type scheme but I cannot see when creating a new issue. what am i missing?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 12, 2020

You can't create sub-tasks without the context of the parent it is going to be part of.  So "create" can't do it. 

Go to the issue that you want to break down and use "create sub-task" from the tools menu