×Can you connect a sub task to more than one issue. If someone worked on a task for more than one issue. Could you link/attach the sub task to both issues vs creating two sub tasks?
No, it is not possible to connect a subtask to more than one parent since it is a strict hierarchy. You can link a issue to a unlimited number of issues.
Best regards,
/Staffan
Hello @Rebecca_Fons ,
Welcome to community!
A sub-task can only belong to one parent task. You have the parent field, which is unique and can only reference one task. What you can do instead is link a sub-task to another task through issue linking.
Link workitem information here: https://support.atlassian.com/jira-software-cloud/docs/link-issues/
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Rebecca_Fons ,
Good day! Welcome to Atlassian community.
No, in Jira Cloud, a sub-task can only belong to one parent issue. This is by design.
Thank you!