can we update the sprint for closed sprint

Ramesh Krishnan
Contributor
May 9, 2025

i would like to update the previous sprint for current story.

Example: Currently i am in Sprint 5.1 for story, which is in progress. Previous sprint is 5.0 which is closed already. i would like to update 5.0 for previous sprint from 5.1. but its not showing old sprint, because of that old sprint not able to update.

3 answers

1 vote
Usman
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 9, 2025

Hello @Ramesh Krishnan 

In Jira Cloud, you cannot directly move a story from an active sprint to a previously closed sprint using the standard Sprint field dropdown, because closed sprints do not appear as selectable options in the UI. However, there are two main workarounds:

Option 1: Reopen the Closed Sprint

  • Go to Reports > Sprint Report on your board.

  • Select the closed sprint (e.g., 5.0) and reopen it.

  • Move the story from Sprint 5.1 back to Sprint 5.0 in the backlog view.

  • Close the sprint again once the move is complete.

This allows you to assign issues to a sprint that was previously closed, but requires temporarily reopening it.

Option 2: Bulk Edit Using Sprint ID

  • Use Jira’s Bulk Change feature:

    • Search for your story in the issue navigator.

    • Select the issue(s), then choose Bulk Change > Edit Issues.

    • In the Change Sprint field, enter the Sprint ID of the closed sprint (you can find the Sprint ID by inspecting the Sprint Report or using browser developer tools).

    • Complete the bulk update.

This method lets you assign issues to a closed sprint without reopening it, but you need the numeric Sprint ID (not the name). https://confluence.atlassian.com/jirakb/jira-software-how-to-search-for-a-sprint-using-jql-779159065.html

Do note that both methods will record the sprint change in the issue history, and this cannot be removed and this process is only available to users with the necessary project permissions.

https://support.atlassian.com/jira/kb/how-to-remove-previously-closed-sprints-from-an-issue/

 

0 votes
Piyush Annadate _ACE Pune_
Community Champion
May 9, 2025

Hello @Ramesh Krishnan ,
Welcome to the Community !
Project -> Reports -> Sprint Report  -> Open the closed sprint -> Make updates and Complete the Sprint.

Here's the full details about reopen a sprint - https://support.atlassian.com/jira-software-cloud/docs/reopen-a-sprint/

0 votes
Sushant Verma
Community Champion
May 9, 2025

Hi @Ramesh Krishnan 

Welcome to the community!

No, Jira does not allow direct editing of a closed sprint's datesHowever, you can reopen a closed sprint, make necessary changes, and then close it again to effectively update the sprint end date to reflect the actual completion date.

Regards,
Sushant Verma