i would like to update the previous sprint for current story.
Example: Currently i am in Sprint 5.1 for story, which is in progress. Previous sprint is 5.0 which is closed already. i would like to update 5.0 for previous sprint from 5.1. but its not showing old sprint, because of that old sprint not able to update.
Hello @Ramesh Krishnan
In Jira Cloud, you cannot directly move a story from an active sprint to a previously closed sprint using the standard Sprint field dropdown, because closed sprints do not appear as selectable options in the UI. However, there are two main workarounds:
Option 1: Reopen the Closed Sprint
Go to Reports > Sprint Report on your board.
Select the closed sprint (e.g., 5.0) and reopen it.
Move the story from Sprint 5.1 back to Sprint 5.0 in the backlog view.
Close the sprint again once the move is complete.
This allows you to assign issues to a sprint that was previously closed, but requires temporarily reopening it.
Option 2: Bulk Edit Using Sprint ID
Use Jira’s Bulk Change feature:
Search for your story in the issue navigator.
Select the issue(s), then choose Bulk Change > Edit Issues.
In the Change Sprint field, enter the Sprint ID of the closed sprint (you can find the Sprint ID by inspecting the Sprint Report or using browser developer tools).
Complete the bulk update.
This method lets you assign issues to a closed sprint without reopening it, but you need the numeric Sprint ID (not the name). https://confluence.atlassian.com/jirakb/jira-software-how-to-search-for-a-sprint-using-jql-779159065.html
Do note that both methods will record the sprint change in the issue history, and this cannot be removed and this process is only available to users with the necessary project permissions.
https://support.atlassian.com/jira/kb/how-to-remove-previously-closed-sprints-from-an-issue/
Hello @Ramesh Krishnan ,
Welcome to the Community !
Project -> Reports -> Sprint Report -> Open the closed sprint -> Make updates and Complete the Sprint.
Here's the full details about reopen a sprint - https://support.atlassian.com/jira-software-cloud/docs/reopen-a-sprint/
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Ramesh Krishnan
Welcome to the community!
No, Jira does not allow direct editing of a closed sprint's dates. However, you can reopen a closed sprint, make necessary changes, and then close it again to effectively update the sprint end date to reflect the actual completion date.
Regards,
Sushant Verma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.