The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Workflow

Deleted user
August 13, 2018

Hi there, 

I created a workflow in Jira for tasks management - really basic: to do, in progress and done. I have managed to change the status from to do and in progress to 'done' before but I can no longer do it. 

I haven't changed anything in the workflow. Would you be able to help please? 

Thank you. 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Mesut Yilmazyildirim
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 14, 2018

The rootcause can be the permissions if you did not change the workflow.

To set DONE status you need Resolve Issues permission in basic workflow. 

First please check if there is a condition as; "Only users with Resolve Issues permission can execute this transition." on DONE transition.

Then, please check if you have resolve issue permission. If you are admin, go to Settings >> System >> Permission Helper and check if you have resolve issue permission

Deleted user
August 16, 2018

Thank you for your help.