The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Why doesn't the version report consider remaining estimate in calculating burn up?

Ben Edelstein
April 29, 2014

I'm trying to use the Jira Agile version report to track progress to our version end date, but it's only considering completed work based on the original estimates for completed issues. We have stories that are partially complete, but it isn't taking the remaining estimates into account to estimate for the predicted end date. This is skewing the results -- seems like a bug? Any options to get the right calculation?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
John Fisher
May 20, 2014

I have the same question -- the estimate for our version report is off by months because it's using the original estimate, and not the remaining work. Help! We are looking to purchase this product, and this is a required feature for us.