Why do I get "x completed issue" with a in progress category and not a done category

LeCour.Antoine
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 22, 2022

Hello,

 

Only when I use Deployment task with a "in progress" category, I get the message of x completed issue when I close a sprint. (with Done it does not work)

 

DO you know why ?

I attached the screen copy of our workflow.

 

Thanks,

Antoineworkflow.JPG

1 answer

0 votes
Trudy Claspill
Community Champion
February 22, 2022

Hello @LeCour.Antoine 

Welcome to the community.

The message "x completed issues" that you see when you close the sprint reflects the number of issues in the right-most column which do not have any open Sub-tasks.

An issue is considered complete at the end of the sprint if the status of that issue is mapped to the board column farthest to the right. It does not matter what Status Category that status belongs to. If you have mapped the Deployment status to the right-most column, then issues in that Deployment status will be considered completed when the sprint is closed. 

LeCour.Antoine
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 22, 2022

Thank you, I get it.

This is in the Board section that you are referring the far right.

Thanks, it works