With the current workflow, we have set up custom resolution states and resolution values, We have 3 states of resolutions:
- QA validated
- Pre-production
- Done
All of our sprints do not capture the stories as "completed" if we do not reach Done. We would like to count the story points if we reach "Pre-production" but looks like Jira is only counting "Done" as the complete state.
Can that be configured?
A sprint will consider an issue "completed" and count its story points if the Status of that issue is mapped to the right-most column of your board.
Can you show us the board setting that show the columns to which each status is mapped?
Thank you!
My mapping was 3 columns:
- ToDo
- In Progress
- In Review
- Failed QA
- Passed QA
- Pre-Pro
- Done
By which all of the statuses to the same column the points are captured properly! I created a TEST project with the right mapping and everything works perfectly now.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.