The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Why backlog task didn't show summed sub-task estimate time

Muk_Chee_Hoe
Contributor
January 17, 2017

Original time estimates from the sub-tasks are summed up when looking at a main tasks detail view, however the sum is not reflected on the board and the board only displays the main task’s original time estimate.

image2017-1-18 15:35:3.png

2 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

3 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 17, 2017

There is a misleading disconnect between JIRA and JIRA Software.

JIRA has a convenient panel that displays the estimates and worklogs from sub-tasks on a parent issue, and provides a couple of functions for summing them up in searches and so-on.

JIRA Software does not expect you to estimate at the sub-task level and does not roll up any data at all.  The story's estimate is the estimate for that story, not the sub-tasks.

This is frustrating for a lot of us. There's several ways to implement "estimate on sub-task" and they're incompatible with each other, so it feels like Atlassian is ducking the question by saying "don't estimate on sub-tasks.

Dominique Morel
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 8, 2017

Hi all.

200% agree with you guys. This just doesn't make sense.

It is so handy to check the SPRINT tasks on the BACKLOG view, BUT so weird (and misleading) to see 'Estimate' value at zero while you made the effort of break-down the original TASK in smaller tasks with ESTIMATE time for each of them, in order to be able to estimate the main original TASK properly (because... that's the purpose of beaking down a task in smaller ones !!...).

Atlassian must provide us with an option to make this addition automatically in this view.

Hoping this will be heard.

Thxs in advance Atlassian.

Like NirNavon likes this
0 votes
NirNavon
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 19, 2024

It is not clear why Atlassian chooses to tell stories instead of fixing this bug when it is clear to everyone that it is a bug