When staring a sprint it's impossible to use the scheduler dates?

Tali Sakel-Liberman
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 3, 2020

find an attachment

error.png

1 answer

1 accepted

1 vote
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 3, 2020

It's the 17:48 - because you have specified h:mm a, it is expecting "5:48 PM", not "17:48"