The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

What set of data is the User Workload report based on?

rewilliams
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 12, 2021

What set of data is the User Workload report based on? Is the entire project backlog OR is it for the current project sprint?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Mohamed Benziane
Community Champion
July 13, 2021

Hi,

Welcome to the community.

The report will show you how much time remaining on all issue assigned to a user by project.

https://confluence.atlassian.com/jiracoreserver073/reporting-861257295.html

Muriel S_ Thiago Ledoux Rupp
Contributor
March 20, 2023

hello @Mohamed Benziane I just can't understand which issues those hours came from, since it only shows the project the hours are allocated.

 

could u provide me the JQL of this report, so I can try to figure out the issues that the report tells me I have X hours of workload?

Muriel S_ Thiago Ledoux Rupp
Contributor
March 20, 2023

I just found it in another post:

assignee={user} and resolved is EMPTY and (timespent > 0 or originalEstimate > 0)