Hi Guys,
Is there any particular setting needed so that the Prediction of Completion date in the Version Report can produce the prediction data?
Community moderators have prevented the ability to post new answers.
Hi @Alfred Tan
On the documentation for this report: https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-version-report/
It describes:
10% of the estimated work for the version will need to be complete before the predictions can be calculated.
Kind regards,
Bill