I currently have 2 projects where the same user is set up only under the "Users" role.  In 1 project, the user is able to view the backlog.  In the 2nd project, they can't.  What could I be missing in the setup of the 2nd project that would explain why the user can't see the backlog?

Thank you!

1 answer

1 accepted

0 votes
Answer accepted
Thomas Deiler
Community Champion
February 12, 2018

Dear @kdukic,

This can have two reasons:

  1. the user has not the permission to see the agile board of 2nd project. Therefore go to 'config board' of the 2nd project's board and have a look on the 'general' tab. Does the user have rights for the project named at 'Shares'?
  2. the 2nd project has a different permission scheme than 1st project. Means that the project role "user" is not mapped to at least the permission "browse project".

So long

Thomas

kdukic
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 14, 2018

Thank you so much!

Suggest an answer

Log in or Sign up to answer