Got redirected by customer and have 10 days left in the current sprint. What are the effects of closing a sprint early? 

1 answer

1 accepted

1 vote
Answer accepted
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 26, 2024

Hi @Jim Weaver -- Welcome to the Atlassian Community!

Are you asking about the impacts to the team or to Jira behavior / reporting for terminating the sprint early?

For the team, I recommend discussing with the team and their coach / scrum master how they handle such occurrences.  Perhaps also review the out-of-the-box guidance from The Scrum Guide for this situation.

For Jira, the reports will just stop earlier than the expected end date, setting the "completed date" to when the sprint is closed.  With the shortened duration, some of the reporting will be impacted, such as for the burn charts and velocity report.  The issues not completed will move to either the next sprint or to the backlog, and the team will need to decide what to do with them.

Kind regards,
Bill

Jim Weaver
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 26, 2024

Thanks Bill, I was wondering about JIRA behavior, I assume this sprints velocity will skew current results until we get additional sprints under our belt.    