The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
  • Community
  • Q&A
  • Jira
  • Questions
  • We are creating projects with shared configuration off a Scrum project but the new project is not created with a Board. Is there a way to fix this?

We are creating projects with shared configuration off a Scrum project but the new project is not created with a Board. Is there a way to fix this?

Steven Klinkerman
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 10, 2016
 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

1 vote
Mathiyalagan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
October 11, 2016

Hi Steven,

       There are two ways you can create the board,

  1. Create the board during project creation.
    1. Go to Agile board - > create a  new Board
    2. Choose new project -> provide the details and submit
    3. It will create project and board as agile scrum
    4. Now, you can update the shared configuration in project scheme
  2. Create a board after project get created,
    1. Go to Agile board - > create a  new Board
    2. Choose existing project -> select the project and submit
Cindy Kapas
May 14, 2018

For Option 1, Step 4, when you say 'update the shared configuration in project scheme', are you referring to updates the different schemes individually?