The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Versions End Date Vs Sprint End Date

Aamer Inam: M-3521
June 5, 2014

Hello ,

I have created two versions in a project that has a release date e.g. June 30 ,2014 . What If my sprint comes to an end before that date , how jira backend engine looks at it or it could be that version date is June 15 ,2014 and my sprint comes to an end as on June 30 ,2014 . I would like to know if there is any logical relation between the two in either case. Look forward to a prompt response.

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
June 5, 2014

It's up to you. You don't HAVE to release at the end of a sprint, and you don't HAVE to release a version just because the sprint ends. The sprint and release, although logically entwined, don't force or require a relationship.