Hi,
based on the explanation on the Atlassian website, the predicted end date in a version report is calculated based on the estimated work still to be done in the version and the average velocity of the team. So: current date + (sum of estimated workload/average velocity). In an example case we have, this means:
Adding that up to today (May 23rd) would mean somewhere mid August.
The version report is predicting Oct 7th 2022.
Can somebody help us on this?
Thanks,
Hans